Project valuation by DCF

A project company is worth the cash it will pay out, discounted for time and risk. How to work it out — and the traps.

By Mayank Jain ·

Build this in Project Finance Studio Read the guide (PDF)

Valuing a project and its equity — 5 pages, free to read.

IRR, NPV and value — NPV against XNPV and IRR against XIRR on real dates, whose cash is whose, and the enterprise value to the equity value. Nothing downloads until you press play. Watch it on Learn, with chapters

What it is

Two viewpoints, one set of cash flows

A project has a finite life, one asset and contracts that fix much of its income. So its value is the present value of the cash it generates — not a multiple of this year’s profit. Two viewpoints matter:

  • The project (unlevered) view — the cash after operating costs, capital costs and tax, before any debt. Is the asset worth building at this price, whoever funds it?
  • The equity view — what is left for the shareholders after the lenders are paid: dividends, shareholder-loan interest and repayments, and the capital returned. Is it a good investment for the sponsors?

How it is worked out

The tools and the rates

NPV = Σ CFt ÷ (1 + r)tevery cash flow discounted to today at the required return, and added up

  • IRR — the discount rate at which the NPV is nil.
  • Payback — the year in which the cumulative cash flow turns positive.
  • MOIC — cash received ÷ cash invested.

No single measure is enough. The IRR says nothing about size, the NPV nothing about the rate, payback nothing about the tail and the MOIC nothing about time. Read them together.

The discount rates

Ke = risk-free rate + β × equity risk premium + specific premium4.0% + 0.8 × 6.0% + 1.0% = 9.8% in the guide’s example

WACC = E ÷ (D + E) × Ke + D ÷ (D + E) × Kd × (1 − t)30% × 9.8% + 70% × 6.0% = 7.14% (no tax in the example, so no tax shield)

Be consistent: nominal cash flows at a nominal rate, real ones at a real rate, linked by (1 + nominal) = (1 + real) × (1 + inflation). Nominal cash flows at a real rate overstate the value badly.

A worked example

A project costs 100 and then produces 10 a year for 20 years. It borrows 70 at 6%, repaid as an annuity of 7.21 a year over 15 years; the sponsors put in the other 30. There is no tax, to keep the arithmetic visible.

  • The project: IRR 7.75%, payback in year 10, MOIC 2.00x.
  • The equity: IRR 10.12%, payback in year 11, MOIC 3.06x.
  • With 10% less cash (9 a year) the project IRR falls to 6.39% but the equity IRR to 6.91%. The lenders’ fixed claim comes first, so every change lands on the equity.

What to watch for

Why the two NPVs disagree, and the traps

In the example the project NPV at the WACC is 4.80, but the equity NPV at its cost is only 0.86. The WACC assumes 70% debt for ever, while project debt is repaid: the gearing falls from 67% to nil by year 15. So project-finance investors value the equity cash flows at the cost of equity, use the project IRR to compare structures, and the lenders’ cover ratios to test the debt.

  • Size. An IRR of 25% on 1 creates less value than 12% on 100. Read it with the NPV.
  • Timing. Cash back earlier raises the IRR even when the total is lower. Check the MOIC too.
  • Reinvestment. The IRR assumes cash is reinvested at the IRR itself; the modified IRR (MIRR) removes that.
  • More than one answer. Cash flows that change sign more than once can have two IRRs, or none. Use the NPV.
  • Dates. Discounting at mid-year raises the example’s project NPV from 4.80 to 8.47. Models on dates use XNPV and XIRR, and state the valuation date.

Buying a stake

Five years in, the equity in the example still has ten years of 2.79 and five years of 10 ahead. At a buyer’s 9% that is worth 34.35. The seller then earns 11.61% on the whole holding — more than the 10.12% of holding to the end — because the buyer accepts a lower return on a project that is built and running. That gap is the reward for taking the construction risk.

Read and watch

The guide and the films

  • The guide · PDF, 5 pages

    Valuing a project and its equity

    NPV, IRR, payback and MOIC; the cost of equity and the WACC; why the project and equity values differ; buying a stake; terminal value.

  • Also in the Knowledge Center · PDF, 4 pages

    LCOE — the levelised cost of energy

    Derived, worked on a 100 MW solar plant and stress-tested: the levelised tariff, three perspectives, real or nominal, and where it misleads.

  • Film · 2:02

    Direct and indirect cash flow

    MJ takes one year's profit to its cash both ways — from EBIT, adding back what is not cash, and by the receipts and payments — and lands on the same number.

Common questions

Should I discount the equity cash flows at the WACC?

No. The WACC goes with the project’s cash flows; the equity’s cash flows are discounted at the cost of equity. A WACC applied to the equity’s cash flows, or the cost of equity to the project’s, is one of the guide’s pitfalls.

Why is the equity IRR higher than the project IRR?

Leverage. Borrowing at 6% to fund an asset that earns 7.75% lifts the equity’s return to 10.12% in the guide’s example. It cuts both ways: with 10% less cash the equity IRR falls further than the project’s.

When should I use XNPV and XIRR?

Whenever the model runs on dates. They discount each cash flow by its actual date. State the valuation date — financial close, today or the date of a sale — and leave out, or roll forward, the cash before it.

Does a project have a terminal value?

Most concessions end with the asset handed back for nothing, so there is none. Assets that keep earning — district cooling, utilities, data centres, land owned outright — do: a growing perpetuity or an exit multiple, cross-checked against each other. When it is most of the NPV, the valuation rests on the distant future.

In the Studio

Build this in Project Finance Studio

Output › Returns shows the project and equity IRR, the NPVs at the cost of capital, the MOIC, the cash yield, the payback and the breakevens. Inputs › Valuation and reporting holds the cost of capital, the end of operations (handed back, an exit multiple or a perpetuity) and the exit valuation for a seller and an incoming partner, and Output › Sensitivity re-runs each change with the debt held. The Excel workbook carries the same formulas.