Valuing a project and its equity
NPV, IRR, payback and MOIC; the cost of equity and the WACC; why the project and equity values differ; buying a stake; terminal value.
A project company is worth the cash it will pay out, discounted for time and risk. How to work it out — and the traps.
By Mayank Jain ·
Valuing a project and its equity — 5 pages, free to read.
What it is
A project has a finite life, one asset and contracts that fix much of its income. So its value is the present value of the cash it generates — not a multiple of this year’s profit. Two viewpoints matter:
How it is worked out
NPV = Σ CFt ÷ (1 + r)tevery cash flow discounted to today at the required return, and added up
No single measure is enough. The IRR says nothing about size, the NPV nothing about the rate, payback nothing about the tail and the MOIC nothing about time. Read them together.
Ke = risk-free rate + β × equity risk premium + specific premium4.0% + 0.8 × 6.0% + 1.0% = 9.8% in the guide’s example
WACC = E ÷ (D + E) × Ke + D ÷ (D + E) × Kd × (1 − t)30% × 9.8% + 70% × 6.0% = 7.14% (no tax in the example, so no tax shield)
Be consistent: nominal cash flows at a nominal rate, real ones at a real rate, linked by (1 + nominal) = (1 + real) × (1 + inflation). Nominal cash flows at a real rate overstate the value badly.
A project costs 100 and then produces 10 a year for 20 years. It borrows 70 at 6%, repaid as an annuity of 7.21 a year over 15 years; the sponsors put in the other 30. There is no tax, to keep the arithmetic visible.
What to watch for
In the example the project NPV at the WACC is 4.80, but the equity NPV at its cost is only 0.86. The WACC assumes 70% debt for ever, while project debt is repaid: the gearing falls from 67% to nil by year 15. So project-finance investors value the equity cash flows at the cost of equity, use the project IRR to compare structures, and the lenders’ cover ratios to test the debt.
Five years in, the equity in the example still has ten years of 2.79 and five years of 10 ahead. At a buyer’s 9% that is worth 34.35. The seller then earns 11.61% on the whole holding — more than the 10.12% of holding to the end — because the buyer accepts a lower return on a project that is built and running. That gap is the reward for taking the construction risk.
Read and watch
The guide · PDF, 5 pages
NPV, IRR, payback and MOIC; the cost of equity and the WACC; why the project and equity values differ; buying a stake; terminal value.
Also in the Knowledge Center · PDF, 4 pages
Derived, worked on a 100 MW solar plant and stress-tested: the levelised tariff, three perspectives, real or nominal, and where it misleads.

Film · 2:02
MJ takes one year's profit to its cash both ways — from EBIT, adding back what is not cash, and by the receipts and payments — and lands on the same number.
No. The WACC goes with the project’s cash flows; the equity’s cash flows are discounted at the cost of equity. A WACC applied to the equity’s cash flows, or the cost of equity to the project’s, is one of the guide’s pitfalls.
Leverage. Borrowing at 6% to fund an asset that earns 7.75% lifts the equity’s return to 10.12% in the guide’s example. It cuts both ways: with 10% less cash the equity IRR falls further than the project’s.
Whenever the model runs on dates. They discount each cash flow by its actual date. State the valuation date — financial close, today or the date of a sale — and leave out, or roll forward, the cash before it.
Most concessions end with the asset handed back for nothing, so there is none. Assets that keep earning — district cooling, utilities, data centres, land owned outright — do: a growing perpetuity or an exit multiple, cross-checked against each other. When it is most of the NPV, the valuation rests on the distant future.
In the Studio
Output › Returns shows the project and equity IRR, the NPVs at the cost of capital, the MOIC, the cash yield, the payback and the breakevens. Inputs › Valuation and reporting holds the cost of capital, the end of operations (handed back, an exit multiple or a perpetuity) and the exit valuation for a seller and an incoming partner, and Output › Sensitivity re-runs each change with the debt held. The Excel workbook carries the same formulas.