Mayank Jain.Project Finance Studio

Risk analysis and PARV

Identify, allocate, quantify — then put a value on each risk with PARV, the probability-adjusted residual value of risk.

By Mayank Jain ·

Build this in Project Finance Studio Read the guide (PDF)

PARV — putting a value on project risks — 6 pages, free to read.

Sensitivities — how sensitivities show what moves your answer: the tornado, the two-way table, breakeven, a COD delay, and the debt held. Nothing downloads until you press play. Watch it on Learn, with chapters

What it is

Who pays if it happens

A project company has one asset and one source of repayment: its own cash flows. The loan is non-recourse or limited-recourse, so if the project fails the lenders can take the project and its contracts, but not the sponsors’ other assets. Every risk is examined twice: can it happen, and who pays if it does.

  • Identify what can go wrong in each phase: development, construction, operation, refinancing, exit.
  • Allocate it to the party best able to control or absorb it: the contractor, the operator, the offtaker, an insurer, the government, the lenders or the sponsors.
  • Quantify what it does to the cash flows, the cover ratios and the returns, and how likely it is.

The allocation matrix is the bridge between the contracts and the model. Construction cost and delay, for example, usually sit with the EPC contractor under a fixed-price, date-certain contract; delay damages and a contingency mitigate them; the model shows them as capex-overrun and COD-delay cases.

PARV then turns the risk register into money, so risks can be compared with each other, with the project’s value and with the cost of doing something about them.

How it is worked out

Sensitivities, the register, then PARV

A sensitivity changes one input and re-runs the whole model. Hold the debt as sized in the base case, and show the equity IRR and NPV for investors, and the minimum and average DSCR, the LLCR and any covenant breach for lenders. Typical ranges are a start, not a rule: capital and operating cost ±10%, output at the P90, COD three to six months late, interest and inflation ±1 point, the tariff ±10%.

A risk register scores each risk’s likelihood and impact from 1 to 5. The rating is likelihood × impact, from 1 to 25 — banded, for example, 1–4 low, 5–9 medium, 10–14 high and 15–25 extreme — before and after the mitigation. A likelihood is better as a probability than a word.

PARV

PARV = (gross value of risk − quantified mitigation) × probability after mitigationthe gross value is the fall in the equity NPV the model gives when the risk happens, with the debt held

PERT value = (best + 4 × most likely + worst) ÷ 6a capital cost overrun of 0%, 8% and 20% gives 8.67%

Run the model at the PERT value, not the worst case: running every risk at its worst and then applying a probability counts the bad news twice.

In the guide’s 50 MW wind farm, with an equity NPV of USD 12.0 mn, six quantified risks have a gross value of 20.73, a quantified mitigation of 4.60 and PARVs that add up to 3.04. Count only the higher of two overlapping risks — the P90 wind and a turbine defect — and apply a 90% overlap factor: the net PARV is USD 2.42 mn, about 20% of the equity NPV.

What to watch for

Counting twice, and the rare, severe risk

  • Re-sizing the debt in a sensitivity or a PARV run — the cover looks fine because the loan shrank.
  • Double counting — “lower wind” and “turbine underperformance” both modelled as lower output, then added.
  • Ignoring correlation — high inflation often comes with high interest rates; move them together.
  • Ranges too narrow — a ±5% capex test on a first-of-a-kind plant says little.
  • A register divorced from the model — scores by gut feel, never checked against a run.
  • Probability and mitigation out of step — a probability before mitigation used with a residual after it.

PARV rewards likely risks and can hide rare, severe ones. In the example the P90 wind could take half the equity’s value, yet its PARV is only 0.60. So escalate on several tests: a severe impact whatever the probability, a high rating whose PARV is under a quarter of its gross value, and a PARV above a threshold the board sets — such as 10% of the equity NPV.

A mitigation is worth buying when it removes more PARV than it costs. In the guide, insurance worth 0.30 today cuts the capital overrun’s PARV from 0.83 to 0.29 — worth it on average, and it takes the risk off the severe-impact list.

Read and watch

The guide and the films

  • The guide · PDF, 6 pages

    PARV — putting a value on project risks

    The probability-adjusted residual value of risk, step by step: PERT three-point estimates, mitigation, overlaps, escalation — on a worked wind farm.

  • The guide · PDF, 5 pages

    Risk analysis in project finance

    Identify, allocate, quantify: the allocation matrix, sensitivities and the tornado, the lenders’ cases, the register and its heat map.

  • Film · 1:03

    A late COD

    Dr. Avya lets the plant finish six months late: the revenue lost, the extra interest, the delay damages, the debt held to its dates and the equity IRR for each delay.

Common questions

What does PARV stand for?

The probability-adjusted residual value of risk: what a risk could still cost after everything that would make good part of the loss, multiplied by how likely it is to happen.

How is PARV different from the expected loss?

The expected loss is the gross value × the probability. PARV first takes off the quantified mitigation — delay damages, a warranty, an insurance claim — so it shows what the project company keeps.

Why use PERT three-point estimates?

One guess hides the range. PERT takes the best case, the most likely and the worst, weights the most likely four times, and gives a value a little above the most likely when the worst case is further away. The model is then run at that value.

Should the debt be re-sized in a sensitivity?

No. Hold the debt as sized in the base case. A re-sized loan shows the downside as a smaller loan instead of a weaker cover, and lenders run their tests with the debt as sized.

In the Studio

Build this in Project Finance Studio

Output › Sensitivity has the tornado, two-way tables, the breakevens and a COD delay of 0–12 months, each a full re-run with the debt held. Output › Risks runs ten quantified and five qualitative risks: the heat map before and after the mitigation, the expected loss and PARV — each risk’s PARV button takes PERT points, the quantified mitigation and a group, with the net PARV, the overlap factor and the escalation flags. The Excel workbook’s Risks sheet carries the same.