PARV — putting a value on project risks
The probability-adjusted residual value of risk, step by step: PERT three-point estimates, mitigation, overlaps, escalation — on a worked wind farm.
Identify, allocate, quantify — then put a value on each risk with PARV, the probability-adjusted residual value of risk.
By Mayank Jain ·
PARV — putting a value on project risks — 6 pages, free to read.
What it is
A project company has one asset and one source of repayment: its own cash flows. The loan is non-recourse or limited-recourse, so if the project fails the lenders can take the project and its contracts, but not the sponsors’ other assets. Every risk is examined twice: can it happen, and who pays if it does.
The allocation matrix is the bridge between the contracts and the model. Construction cost and delay, for example, usually sit with the EPC contractor under a fixed-price, date-certain contract; delay damages and a contingency mitigate them; the model shows them as capex-overrun and COD-delay cases.
PARV then turns the risk register into money, so risks can be compared with each other, with the project’s value and with the cost of doing something about them.
How it is worked out
A sensitivity changes one input and re-runs the whole model. Hold the debt as sized in the base case, and show the equity IRR and NPV for investors, and the minimum and average DSCR, the LLCR and any covenant breach for lenders. Typical ranges are a start, not a rule: capital and operating cost ±10%, output at the P90, COD three to six months late, interest and inflation ±1 point, the tariff ±10%.
A risk register scores each risk’s likelihood and impact from 1 to 5. The rating is likelihood × impact, from 1 to 25 — banded, for example, 1–4 low, 5–9 medium, 10–14 high and 15–25 extreme — before and after the mitigation. A likelihood is better as a probability than a word.
PARV = (gross value of risk − quantified mitigation) × probability after mitigationthe gross value is the fall in the equity NPV the model gives when the risk happens, with the debt held
PERT value = (best + 4 × most likely + worst) ÷ 6a capital cost overrun of 0%, 8% and 20% gives 8.67%
Run the model at the PERT value, not the worst case: running every risk at its worst and then applying a probability counts the bad news twice.
In the guide’s 50 MW wind farm, with an equity NPV of USD 12.0 mn, six quantified risks have a gross value of 20.73, a quantified mitigation of 4.60 and PARVs that add up to 3.04. Count only the higher of two overlapping risks — the P90 wind and a turbine defect — and apply a 90% overlap factor: the net PARV is USD 2.42 mn, about 20% of the equity NPV.
What to watch for
PARV rewards likely risks and can hide rare, severe ones. In the example the P90 wind could take half the equity’s value, yet its PARV is only 0.60. So escalate on several tests: a severe impact whatever the probability, a high rating whose PARV is under a quarter of its gross value, and a PARV above a threshold the board sets — such as 10% of the equity NPV.
A mitigation is worth buying when it removes more PARV than it costs. In the guide, insurance worth 0.30 today cuts the capital overrun’s PARV from 0.83 to 0.29 — worth it on average, and it takes the risk off the severe-impact list.
Read and watch
The guide · PDF, 6 pages
The probability-adjusted residual value of risk, step by step: PERT three-point estimates, mitigation, overlaps, escalation — on a worked wind farm.
The guide · PDF, 5 pages
Identify, allocate, quantify: the allocation matrix, sensitivities and the tornado, the lenders’ cases, the register and its heat map.

Film · 1:03
Dr. Avya lets the plant finish six months late: the revenue lost, the extra interest, the delay damages, the debt held to its dates and the equity IRR for each delay.
The probability-adjusted residual value of risk: what a risk could still cost after everything that would make good part of the loss, multiplied by how likely it is to happen.
The expected loss is the gross value × the probability. PARV first takes off the quantified mitigation — delay damages, a warranty, an insurance claim — so it shows what the project company keeps.
One guess hides the range. PERT takes the best case, the most likely and the worst, weights the most likely four times, and gives a value a little above the most likely when the worst case is further away. The model is then run at that value.
No. Hold the debt as sized in the base case. A re-sized loan shows the downside as a smaller loan instead of a weaker cover, and lenders run their tests with the debt as sized.
In the Studio
Output › Sensitivity has the tornado, two-way tables, the breakevens and a COD delay of 0–12 months, each a full re-run with the debt held. Output › Risks runs ten quantified and five qualitative risks: the heat map before and after the mitigation, the expected loss and PARV — each risk’s PARV button takes PERT points, the quantified mitigation and a group, with the net PARV, the overlap factor and the escalation flags. The Excel workbook’s Risks sheet carries the same.